STEEL ERECTION
  • Fabricator:  HME
  • 335,000 sf; 13,000 Tons
  • Mobilization to completion:  17 months
  • Project consisted of 3 hangars, one bay, two bays, and three bays, used to house the KC-46A planes. LPR’s inhouse pre-construction engineers established a plan and calculated the critical lifts to erect each building by assembling truss assemblies on the ground and hoisting sections weighing in excess of 300,000 lbs utilizing 2 – 300 ton cranes to achieve a tandem lift.

Location:

Wichita, KS

Client:

Archer Western Aviation Partners (Walsh, Alberici, Flintco)