STEEL ERECTION

Description:

The need came from Aims’ continuous growth in capacity, but also in community. This new welcome center will be a space for admissions, academic advising, financial aid and other student services.  The auditorium will host college-wide events.  LPR’s Preconstruction Engineers had to battle through the complex design that had a web of structural steel including 70 feet + long trusses that had to be support on LPR designed shores.

  • Fabricator: Zimmerman Metals, Inc
  • Mobilization to completion: 5 months
  • Project is 125,000sf and 1,100 tons

Location:

Greeley, CO

Client:

Fransen Pittman Construction Co.